2020.09.30 E,N mudroom walls up
2020.10.01 W mudroom and N wall up
2020.10.05 add E and center support walls
2020.10.07 second floor joists
2020.10.13 interior walls and second floor subfloor
2020.10.19 roof jacks in action, second floor N wall
2020.11.02 garage roof sheathing
2020.11.07 roof sheathing and membrane complete
2020.11.19 backfilling with slinger
2020.11.26 electrical service, crawlspace mold
2020.12.23 roofing, papering, staining
2021.01.19 front porch going up
2021.01.28 windows, posts, beams
2021.02.02 windows, paint drying, porch roof
2021.04.15 A34 fix for blocking supporting porch rafters
2021.04.30 concrete for beam fix, etc.
2021.07.18 garage siding, electrical service
2021.08.28 prepare to demolish shed
2021.12.14 garage floor finishing
2022.04.26 crawlspace plumbing